Hostname: page-component-8448b6f56d-42gr6 Total loading time: 0 Render date: 2024-04-23T11:39:26.835Z Has data issue: false hasContentIssue false

Reducing levels of Violence in the Psychiatric Intensive Care Unit (PICU) - a multidisciplinary quality improvement project

Published online by Cambridge University Press:  18 June 2021

Zoe Moore*
Affiliation:
Belfast Health and Social CareTrust
Lynne Pritchard
Affiliation:
Belfast Health and Social CareTrust
llana Hamilton
Affiliation:
Belfast Health and Social CareTrust
*
*corresponding author.
Rights & Permissions [Opens in a new window]

Abstract

Core share and HTML view are not available for this content. However, as you have access to this content, a full PDF is available via the ‘Save PDF’ action button.
Aims

Our aim: To reduce the number of Level 1* violent incidents in Ward 4 by 30% by April 2020

*Level 1 is defined as “Behaviour involving force, which causes or is intended to cause physical harm to others; but excludes assault on objects, threats or verbal abuse”

Ward 4 is Belfast Health and Social Care Trust's only PICU, with a total of 6 beds. Our project took place on the background of a recent move to a new purpose-built inpatient unit, as well as a trust-wide initiative to address levels of violence across inpatient psychiatry services.

Method

We divided our project into 3 main areas:

Patient factors

Staff factors

Environmental factors

We identified and implemented a number of change ideas, using Plan-Do-Study- Act methodology, regularly meeting to review progress and plotting our data on a run chart.

Key patient interventions included a “Mutual Respect” exercise and regular “Community Meetings”.

Staff interventions included use of Safety Crosses, Daily Safety Briefings and the Broset Violence Checklist (BVC).

Environmental factors were continually assessed and escalated as appropriate.

We raised awareness of our project and gained feedback by creating a dedicated notice board, providing a staff information session and including it as an agenda item at ward meetings.

Our project measures were identified as:

Outcome: Number of level 1 violent incidents occurring per week

Balancing: Number of incidents in other categories; Patient satisfaction

Process: Staff safety rating; Engagement with interventions

Result

Unfortunately, we were unable to meet our initial goal and there continued to be considerable variation in the number of weekly incidents.

We believe this was attributable to several factors, including the level of acuity within the ward during the project timeframe. It was noted that a relatively small number of patients contributed to a large proportion of the total incidents. Our results, therefore, did not reflect the success of interventions with other patients on the ward.

Despite this, we noted improvements in terms of patient and staff engagement with the project, including subjective reports of staff safety during shifts.

Conclusion

The unpredictable and complex nature of the PICU setting cannot be under-estimated and this ultimately impacted on achieving our intended outcome.

We do feel, however, that the project has had a positive impact and we hope we can build on this progress over the coming months.

Further interventions are being explored, including personalised daily activity schedules and attempts to reduce levels of continuous observations.

Type
Quality Improvement
Creative Commons
Creative Common License - CCCreative Common License - BY
This is an Open Access article, distributed under the terms of the Creative Commons Attribution licence (http://creativecommons.org/licenses/by/4.0/), which permits unrestricted re-use, distribution, and reproduction in any medium, provided the original work is properly cited.
Copyright
Copyright © The Author(s), 2021. Published by Cambridge University Press on behalf of the Royal College of Psychiatrists
Submit a response

eLetters

No eLetters have been published for this article.